The temporary facilites are dismounted after the bridge shifting. The curbs are reconstructed on both sides of the structure and the railway technical installations such as the contact line and the cable trough are positioned. At last, the old masonry bridge is cleaned, and some outdoor design and replanting is done before reopening the underpass to traffic.